ASTEP I.S. – Case Study
ASTEP I.S. GoA 50 km Case Study Field Definition Basis

ASTEP Platform Specification: 50 km Gulf Coast Case Study
Hull and Deck Specification
- Normally unattended platform
- Proven GVA twin pontoon semi submersible
- Deck 64 x 64 m
- Hull Displacement: 25,000 Te Draft: 21 m Freeboard: 22.5 m
- 8 point-mooring
In-line tension chain-poly-chain
suction piles
- 30-year design life
- 1 Fuel-gas riser + future riser hang-off
- 3 umbilicals (1 HV-MPP, 1 HV-ATM, 1 E-H Controls)

Topside Equipment Specification

GTG Power Generation 7.5MW peak demand @ n+1 w/ diesel restart
VSD Subsea Multiphase Pump 3.65MW peak demand
Subsea Heating System DEH with 5.0MW peak demand
Chemical Injection Skid
Hydrate Inhibitor: 75 bbl
Corrosion Inhibitor: 736 bbl
Wax Inhibitor: 0 bbl due to ATM system
Asphaltene/Scale Inhibitor: 435 bbl
Subsea Well Control Module
Control and Communication Module
Utility and Material Handline 1 Pedestal crane Walk to work landing/connection
ASTEP I.S. Case Study Project Execution – Post FID
PLATFORM
SUBSEA
ENGINEERING HOUSTON

Engineering 8 Months
- Engineering 8M before steel cutting
- Bulk order 5M before steel cutting
- Procurement 7M before steel cutting

ENGINEERING

Engineering 2 Months
- High-Level FEED completed prior to FID to enable long-lead procurement
- Long-lead procurement at FID

FABRICATION FAR EAST

Fabrication 12 Months
- Block fabrication and erection
- Equipment installation
- Commissioning

FABRICATION

Fabrication 18 Months
- Long lead billet and forgings control
- Includes FAT and SIT

DRY TRANSPORTATION

Dry Transport 2 Months
- Far East to Gulf of Mexico (Gulf of America)

INSTALLATION

SPS Installation 2 Months
- SPS and flowlines

HOOK-UP AND COMMISSIONING GULF OF MEXICO (GULF OF AMERICA)

Hook-Up and Commisioning 2 Months
- Mooring Hook-up
- Umbilical Installation
- Fuel Gas Riser
- Commissioning
First Oil: 24-30 Months after FID
Conventional vs. an ASTEP I.S. Tieback
A GOM Case Study is presented comparing ASTEP I.S. Solution to a conventional tieback approach.

Cost Estimate
ASTEP I.S. 50 km Gulf Coast Case Study Cost Estimate (%)

[1] Pricing based upon Q1 2021 KBR norms and industry pricing [2] All estimates are Class 5 in current dollars and exclude: owner’s costs, escalation/inflation, project level contingency, taxes, duties, DRILLEX and fees [3] Includes Fabricator EPCM and 10% design allowance


ASTEP I.S.
Autonomous Subsea Tieback Enabling Platform Integrated System
© 2025 KBR Inc. All rights reserved
